01 | THE RIGHT ACTION AT THE WRONG TIME

A program can contain the correct calculation, input and output statements and still fail because they occur in the wrong order. Printing a total before calculating it is like handing out a receipt before knowing what was bought.

A sequence is the order in which instructions execute. A correct sequence respects dependencies: obtain information before using it, establish valid state before changing it, and report a result after the required operation succeeds.

This common SL/HL lesson develops complete Python programs and traces instruction order. It also covers incorrect output, infinite loops and deadlock, including why those failures require different explanations.

02 | BEGIN WITH AN OBJECTIVE

Suppose the objective is: receive a valid whole-number ticket count, charge 4.50 per ticket, apply a ten-percent discount to the subtotal and display the discounted total to two decimal places.

The objective determines the necessary dependencies. The ticket count must exist before its subtotal can be calculated; the subtotal must exist before its discount; both values must exist before the final total.

Write down the expected result for a small example. Three tickets give subtotal 13.50, discount 1.35 and final total 12.15. This lets you judge the sequence rather than merely check that the program runs.

03 | INPUT, PROCESS, OUTPUT

raw = input("Tickets: ")
tickets = int(raw)
subtotal = tickets * 4.50
discount = subtotal * 0.10
total = subtotal - discount
print(f"{total:.2f}")

The program follows input → conversion → calculation → output. Assume valid numeric input in this first version. input supplies text; int produces the integer used by multiplication.

The f-string formats the final number to two places. Formatting changes presentation, not the underlying approximate binary floating-point representation. These are small teaching values, not a complete financial calculation policy.

The statement order is not arbitrary: later expressions require values produced earlier. We will add validation and safe failure routes after understanding the successful path.

04 | ASSIGNMENT READS THE RIGHT SIDE FIRST

total = 10
new_value = 4
total = total + new_value
print(total)  # 14

Evaluate total + new_value using the current values 10 and 4, then store 14 in total. The old total is read before that name is rebound.

Changing the order can change the inputs to the calculation. If total = 0 executes immediately before the update, the result becomes 4 rather than 14.

A sequence is a series of state changes. Trace what each name holds at the moment an expression reads it, rather than relying on the value it had earlier or will have later.

05 | A DEPENDENCY MAP

Instruction Needs beforehand Produces or does
raw = input(...) An input source Text value raw
tickets = int(raw) Suitable raw text Integer tickets
subtotal = tickets * 4.50 tickets subtotal
discount = subtotal * 0.10 subtotal discount
total = subtotal - discount subtotal and discount total
print(f"{total:.2f}") total Formatted output

Independent instructions can sometimes be reordered without changing required behaviour. The point is to satisfy dependencies and observable effects, not to memorise one universal line order for every program.

In this particular six-line example, the chain of dependencies requires the displayed order. An assignment to an unrelated configuration name could have more than one valid placement.

06 | READING BEFORE ASSIGNMENT

# Incorrect: tickets has not been assigned.
subtotal = tickets * 4.50
tickets = 3

In a fresh module, this raises NameError at the first line. The later assignment does not travel backwards in time to make the earlier read valid.

Inside a function, a local read before a local assignment can instead produce UnboundLocalError. The precise exception depends on the scope and operation.

Interactive environments can hide this bug if a name remains from an earlier run. Test from a clean state as well as from a convenient existing session.

07 | INCORRECT OUTPUT WITHOUT AN EXCEPTION

total = 0
print(total)
total = 12.15

This program validly prints 0. It then assigns 12.15, but does not print again. No exception is needed for the output to violate the objective.

Move the output after the required calculation. Do not claim that a later assignment automatically changes text already printed.

Check output order too. A prompt should appear before the relevant input; a success confirmation should follow an operation that actually succeeded.

08 | ORDER CAN CHANGE AN ARITHMETIC RESULT

subtotal = 100.0
subtotal = subtotal * 0.90
subtotal = subtotal + 5.0
print(subtotal)  # 95.0

This discounts 100 to 90, then adds a fixed charge of 5, giving 95. If the charge is added first and the ten-percent discount is then applied to 105, the result is 94.5.

Neither sequence is universally correct. The specification must say whether the charge is included in the discounted amount. A difference in outputs is evidence of different rules, not automatically evidence that one arithmetic operator is broken.

Keep named intermediate values when they make the intended order clearer.

09 | INTERACTIVE: CONSTRUCT THE SIX-LINE PROGRAM

Arrange the ticket program using the up/down controls, then check and trace it. The input is assumed to be a valid whole number from 0 to 20. The activity executes only the supplied statements; it is not an arbitrary Python interpreter.

Identify the first read whose required value does not yet exist. A correct result includes a trace of the named values and the final output. Moving a statement clears the old feedback.

10 | SEQUENCE INSIDE FUNCTIONS

def final_cost(tickets):
    subtotal = tickets * 4.50
    discount = subtotal * 0.10
    total = subtotal - discount
    return total

answer = final_cost(3)
print(f"{answer:.2f}")

The definition creates the function. Its body executes on the call final_cost(3). The caller waits for the returned value, binds it to answer and then prints it.

Returning before a necessary calculation prevents the later statements in that call from being reached. Printing inside a function is not a substitute for returning a result the caller needs.

Define a function before an execution path calls it. A function may refer to another name that is established later in source order, provided it exists when that reference actually executes; follow runtime order rather than assuming every definition immediately runs its body.

11 | VALIDATE BEFORE THE DEPENDENT OPERATION

raw = "3"
try:
    tickets = int(raw)
except ValueError:
    print("Enter a whole number")
else:
    if 0 <= tickets <= 20:
        total = tickets * 4.50 * 0.90
        print(f"{total:.2f}")
    else:
        print("Tickets must be from 0 to 20")

Invalid numeric text follows the handler rather than reaching multiplication with an unassigned tickets value. A converted integer still needs the required range check before processing.

If validation is performed only after a booking is saved or a payment request is sent, it may be too late to prevent the unwanted effect. Order checks before consequential operations.

Exception handling can support the intended routes, but it does not repair a wrong discount rule.

12 | KEEP SUCCESS OUTPUT ON THE SUCCESS PATH

Imagine a save operation fails because a resource is unavailable. Printing “Saved” after an unconditional handler would mislead the user if the failed path still reaches it.

Place success output after confirmed success, or use a control structure that returns or branches appropriately on failure. The handler should report the actual outcome.

The same principle applies to jobs: removing a job from a queue is not proof it completed, and starting a file write is not proof every required record was stored. Define the operation’s success condition.

13 | INITIALISE ONCE OR RESTART DELIBERATELY?

values = [4, 7, 2]
total = 0
for number in values:
    total = total + number
print(total)  # 13

total begins before the loop so each iteration preserves earlier contributions. Moving total = 0 inside the loop would reset the accumulated value before every addition.

For a 2D row-total task, resetting row_total inside the outer row loop is intentional, while a grand_total remains outside it. Initialisation placement follows the variable’s purpose.

A correct statement can therefore be in the wrong region even if it appears before the line that uses it.

14 | INFINITE LOOPS: NO ROUTE TO THE EXIT

count = 1
while count <= 3:
    print(count)
    count = count + 1

This loop outputs 1,2,3 and exits after count becomes 4. The continuation test is evaluated again using the updated value.

If the increment is removed, count stays 1 and the condition remains true. That gives an infinite run for this initial state. The missing state change explains the failure.

Not every intentionally ongoing event loop is a bug, but a task required to finish needs a justified exit path or an appropriate interruption policy.

15 | AN UPDATE CAN EXIST BUT NEVER BE REACHED

count = 1
while count <= 3:
    if count == 2:
        count = count + 1
        continue
    print(count)
    count = count + 1

This version prints 1 and 3, skips output for 2 and still terminates. The skip branch increments before continue, while the normal branch increments at the end.

If continue comes before the increment in that skip branch, the increment is unreachable. When count reaches 2, it repeatedly takes that branch without changing count.

Avoid the problem by arranging an update on every continuing route, or by using a counted loop where its iteration mechanism suits the task. Simply spotting an increment somewhere in the source is not enough.

16 | WAITING FOR INPUT IS NOT AUTOMATICALLY AN INFINITE LOOP

A program paused at input may be waiting for a person. A program blocked on a resource may be waiting for another task. A loop repeatedly executing with an unchanged true condition is a different behaviour.

Inspect where execution is paused and what event could let it proceed. A user supplying input may resolve a legitimate wait; it cannot fix a missing count increment inside a tight loop.

Timeouts and cancellation can help some external waits, but they require a defined response. A timeout alone does not prove that every resource was released or that retry is safe.

17 | DEADLOCK: TASKS WAIT ON EACH OTHER

A deadlock can occur when tasks hold resources while waiting in a cycle for resources held by one another. This is different from a single loop repeatedly computing.

Suppose Task A holds a printer lock and needs a scanner lock. Task B holds the scanner lock and needs the printer lock. Neither releases its held lock until it obtains the other. Each is waiting for the other task to move first.

A lock controls access to a shared resource or critical section. The example is about software resource ownership; it does not claim physical devices necessarily expose exactly these locks.

18 | THE ORDER THAT CREATES A CIRCULAR WAIT

Step Task A Task B Consequence
1 Acquire printer lock Not yet running Printer held by A.
2 Still holds printer Acquire scanner lock Scanner held by B.
3 Request scanner; wait Still holds scanner A waits for B.
4 Still waiting Request printer; wait B waits for A; circular wait.

Each task’s individual plan might look plausible: get one resource, then the other, then work. The interaction creates the failure because resources are acquired in opposite orders.

Deadlock requires the waiting conditions in the model. Two tasks merely running slowly, or one task waiting while its owner can finish and release, is not by itself evidence of deadlock.

19 | A CONSISTENT RESOURCE ORDER CAN PREVENT THIS CYCLE

Require both tasks to acquire printer before scanner. If A holds printer, B waits for printer without holding scanner. A can then obtain scanner, complete its work and release both resources. B can proceed afterwards.

A consistent global ordering prevents circular wait among the locks governed by that ordering. All relevant tasks must follow it; unrelated locks or a different dependency can create other problems.

Use appropriate resource cleanup even when work fails, and avoid unnecessary resource holding. Acquisition policies, bounded waits and recovery designs require context; one corrected two-lock example is not a universal guarantee that concurrent software cannot deadlock.

20 | INTERACTIVE: COMPARE TWO LOCK ORDERINGS

Step through a specified two-task schedule. The unsafe schedule gives the tasks opposite resource orders. The safe schedule gives both printer-then-scanner order. This is a model of lock ownership and waiting, not an actual concurrent hardware operation.

At each pause, say who owns each lock and whether a waiting task can be unblocked by an owner that is still able to proceed. The final unsafe state has no next successful step under its stated rules.

21 | DISTINGUISH THE FAILURE MODES

Behaviour Example Investigation / response
Incorrect output Print before the correct assignment. Trace dependencies and move output to the required route.
Infinite loop Every continuing route skips the needed update. Inspect state changes and exit conditions.
Deadlock A holds printer and waits for scanner; B holds scanner and waits for printer. Inspect ownership/wait cycles and coordinate acquisition order.
Legitimate wait A task waits while another can finish and release its resource. Check the owner’s progress and the expected wake-up event.

Do not diagnose all non-response as “an infinite loop”. The relevant evidence may be changing variables, a blocked input, call stacks, lock ownership or an unavailable external service.

22 | CONSTRUCT A COMPLETE ORDERED SOLUTION

A workshop has 12 available places and charges 4.50 per place. Given text for a requested quantity, construct a program that converts and validates it, checks sufficient places, calculates cost, updates remaining places and only then confirms the accepted booking. Reject invalid or excessive requests without reducing availability.

For this small model, requests are processed one at a time and data is in memory. No payment or persistent save is attempted. A real multi-user booking service needs suitable coordination and transaction/error handling.

Reveal one possible solution
def book_places(raw, available):
    try:
        requested = int(raw)
    except ValueError:
        return available, "Enter a whole number"
    if requested <= 0:
        return available, "Request must be positive"
    if requested > available:
        return available, "Not enough places"
    cost = requested * 4.50
    remaining = available - requested
    return remaining, f"Accepted: {requested}; cost {cost:.2f}"

available, message = book_places("3", 12)
print(message)
print("Remaining:", available)

The result is Accepted: 3; cost 13.50, followed by Remaining: 9. Every rejected route returns unchanged availability. Multiple return values are unpacked into the two names at the call site.

23 | TEST ORDER, STATE AND OUTPUT

Test Expected evidence
Ticket input3 Subtotal13.50, discount1.35, total/output12.15.
Invalid numeric text Conversion response; no successful result based on an unassigned value.
Booking3 from12 Acceptance and remaining9.
Booking13 from12 Rejection and remaining12.
Loop count1 to3 Outputs1,2,3 and terminates.
Skip count2 branch State still advances; no endless repeat at2.
Opposite two-lock ordering Demonstrable circular wait under the stated schedule.
Common two-lock ordering Owner can finish/release and waiting task can proceed.

Use clean initial state and inspect intermediate values. A final total can accidentally match while output timing, resource ownership or a rejected-path update is still wrong.

24 | A CONSTRUCT ANSWER NEEDS CODE

Produce a program meeting the objective, not only an account of sequence. Make initialisation, input/conversion, validation, calculation, state changes and output clear. Use indentation to identify the paths.

Explain assumptions when a task leaves concurrency, input validity or failure policy unspecified. Do not present a classroom sequential model as a fully coordinated production system.

Trace at least one successful and one rejected case before judging your sequence.

25 | COMMON MISTAKES

Do not read a name before the path assigns it, reset a total at the wrong loop level, print stale state, skip an essential update with continue or confirm success after a failed operation.

For resource use, do not acquire the same set of locks in inconsistent orders across cooperating tasks. Release what was acquired appropriately; unexpected failure must not silently leave shared resources held.

Avoid fixing an example by hardcoding its expected output or hiding every exception. Correct the dependency or control-flow cause, then retest.

26 | READY FOR SELECTION AND REPETITION

You can now connect instruction order to data dependencies, observable output, termination and resource waiting. These ideas apply inside branches, loops and functions as well as in a short straight-line program.

The next lesson constructs selection structures, where conditions choose which sequence executes.

MATCH THE SEQUENCE IDEA

Terminology

Terminology

Sequence

The order in which program instructions execute.

Program objective

The required behaviour or outcome a program must achieve.

Dependency

A requirement for a value or state to exist before another action can use it.

State

Current values and relevant execution conditions.

Assignment

Evaluating an expression then binding its result to a name.

Initialisation

Establishing a starting value before it is used.

Input

Data received by a program or process.

Conversion

Producing a value of another type from suitable data.

Validation

Checking whether data meets the task’s rules.

Processing

Operations that transform data or update relevant state.

Output

Information produced for a user or another process.

Stale value

An earlier value used or displayed before the needed update.

Control flow

The route taken through instructions during execution.

Reachable statement

A statement that can actually be executed on a relevant path.

Unreachable statement

A statement that cannot be reached on the path being considered.

Loop continuation condition

The condition under which a loop body executes or repeats.

Infinite loop

A repetition that never reaches its required exit under the given conditions.

Progress update

A state change that helps execution approach a loop’s exit or task completion.

continue

A control statement moving to the next loop iteration, skipping the rest of the current body.

Deadlock

A situation where tasks are stuck waiting on dependencies such as a cycle of held resources.

Resource

Something a task needs, such as a connection, file handle or shared service.

Lock

A mechanism controlling access to a shared resource or critical section.

Ownership

Which task currently holds a resource/lock in the model.

Circular wait

A cycle in which tasks wait for resources held by one another.

Global lock order

A consistent acquisition ordering followed by relevant tasks for the governed locks.

Cleanup

Releasing or restoring resources on the appropriate exit paths.

Timeout

A limit on a wait, requiring a defined response when exceeded.

Atomicity

An operation taking effect as one unit rather than exposing a partial change.

Trace

Follow and record actions and state during execution.

Rejected path

A route that refuses an operation and should preserve the specified unaffected state.

Questions

Questions

CHECK YOUR UNDERSTANDING

Select all correct choices. Each exact set earns one point.

1. Which explain instruction dependencies?
2. Which follow the ticket objective?
3. Which describe incorrect output?
4. Which are valid order-sensitive claims?
5. Which support valid rejected paths?
6. Which explain loop termination?
7. Which distinguish waits?
8. Which describe the unsafe lock example?
9. Which qualify the common lock-order remedy?
10. Which improve verification?

EXPLAIN AND COMPARE

Write your answers before revealing each sample.

1. Construct the six-line ticket calculation in dependency order.

2. Explain why reading tickets before assignment can fail.

3. Trace total=0; print(total); total=12.15.

4. Explain the difference between discount-then-charge and charge-then-discount.

5. Construct a terminating loop outputting1,2,3.

6. Explain why an increment placed after continue can fail to ensure termination.

7. Distinguish an infinite loop from the two-task deadlock.

8. Explain the circular wait in the printer/scanner example.

9. Explain how consistent acquisition order prevents the modeled cycle.

10. Construct the rejected paths of the workshop booking function.

11. Explain why success confirmation must follow confirmed success.

12. Describe tests demonstrating correct instruction order.

CONSTRUCT IT | A TRUSTWORTHY REPORT

A report program must read numeric text, reject unsuitable values, calculate an average for a positive count and display the result only after success. Construct its sequence in Python. Identify one incorrect placement that would create an error or misleading output. Describe a suitable test.

Reveal an approach

Convert supplied text under a specific handler, reject a nonpositive count before division, calculate the result and print it only on the successful route. A success print after a failure handler can mislead, and division before validating zero can raise. Test valid input, invalid text and zero separately.

Flashcards

Flashcards

Click to flip. Select the ideas you need to revisit.

0 cards selected for revision.

Selections are kept while this page is open.

Workbook

Workbook

COMING SOON

The workbook for B2.3.1 Instruction Sequence is coming soon. Complete the matching task and written questions in your exercise book.